PK 389Q – Universal Pre K

PK 389Q – Universal Pre K

Client: New York City School Construction Authority (SCA)

Contact: Frank Pagano, Senior Project Officer / 718-752-5692 / fpagano@nycsca.org

Construction Value: $8,500,000.00

Project Duration: 12/24/2014 – 6/20/2015

Project Features:

Complete Demolition of 1st floor and partial demolition of basement
Construction of new classroom, principal office, staff rooms, Pantry etc.
Installation of new furniture including tables, chair, smart boards etc.
Installation of new ceiling and flooring
Remove and replace entire roof
Installation of Ramp to fulfill ADA requirement in playground
Installation of new 2 RTU, AC unit and radiator for HVAC
New service, lighting, power, data, fire alarm and security system in entire building
Playground (Equipment and Tiles)/Landscaping Restoration